Site Address:
Bridge street, Wye
Sector:
Domestic
Project Source:
Website
Scope Of Works:
- Demolition and clearance of the existing conservatory and extension.
- Excavate and install new strip foundations.
- Set up a dewatering system to allow this to happen due to the high water table.
- Build a block and brick substructure.
- Supply and install block and beam flooring.
- Hand over to the client, ready for the builder to start the extension.
Size Of Team:
Labour and plant;
- 2 x Men for 14 days
- 3t Excavator
- Skip Dumper
- Water Pumps